The Industrial Wastewater Treatment contract has been awarded from one of our International Multinational Customers, the scope of work of shall include Finance, Design, Fabrication, Manufacture, Assembly, Packing, Transportation and Unloading, Storage at Site, Erection, Testing, Commissioning.

           

Also carrying out Performance Guarantee Tests and Operation of the IWWT Plant of 2,500 m3 per day for 10 years on Build Own Operate Transfer (BOOT) basis, the major scope includes but not limited to:

All Civil Works within IWWT Plant
Headworks such as Screening
Pre-Treatment for SS Removal
Advanced Oxidation
Secondary Treatment & Disinfection
Water Recycling System
Zero Liquid Discharge System

The 2,500m3 per Day IWWT Plant has been designed to remove COD, BOD, TDS, TSS, and FOG and the project will start on site from April 2024 with an estimated completion date in May 2026.